Interested Parties Report (photos)

Project activities update for the week ending: 10/23/2020 Site survey, retention pond, erosion controls, equipment mobilization. 10/30/2020 Retention pond grading, mobilization, site prep, foundation staking, and erosion controls underway. 11/6/2020 Pond seeded and has straw down for erosion control, foundation grade beams excavated, construction sign up, final trailer mobilization for …