Draft Board Meeting Minutes – September 23, 2023

Draft Board Meeting Minutes – September 23, 2023

Call to Order:

Welcome: April, President

Present/Quorum: Dave (Manager), Paul, April, Todd, Clint, Sam, Darton

Consent Items

Approve – Contents and order of this Agenda: Approved.

Approve – Minutes of August meeting: Approved.

Information Items

Guest Speakers comments (if any): None

Board Member comments (if any): None

President’s Report (April)

  • N/A

Manager/Operator Report (Dave)

  • Alarms and communication for Sandy Shores, S&B is coming up with a package that is common for water facilities. Could cost $2-3k, with the antenna array being additional. Should solve our communications issues.
  • It will include communications for the silo.
  • G&O has identified areas around the springs designated as wetlands. Survey work will come out next week.
  • Water main break in Sandy Shores – We’ve paid for the pumping of her septic tank and she needs us to clear her new driveway. Dave cleared it out yesterday.
  • BHC for PRV location project should be submitting to 60% design soon. Stay tuned.
  • At the springs – The control cabinets backup battery device was beeping. Both batteries have gone bad. New batteries have been ordered.
  • Booster pump station – The motor for the 3/4 HP pump was burnt out, the existing backup pump motor was used, we need to replace the backup.

Committee Reports:

Finance Committee (Todd):

  • Revenues are starting to pick up related to the rate change. We should be well ahead of budget by November.
  • Costs – Business Ops is very under budget
  • Systems ops are a little high, perhaps related to propane purchase and the chlorine pump hit operations pretty hard. The chlorine pump was included in small tools budget.
  • We moved $100,000 from our checking account (US Bank) to a savings account at Kitsap Bank, which should provide some interest income.
  • We still have a sufficient cushion in our checking account for cash flow needs. 
  • Online billing – We have the info we need to continue those conversations – web-based billing portal for our customers.
  • Based on preliminary Sept numbers – we have about $100 a month going out and we’re collecting about $50.

Water Production Committee (Paul):

  • Dave covered most issues
  • Silos – Mount Baker Silos – We’re 40 years in on a 50 year cycle, we could go 70 years if we baby it, he’s going to come out in the spring.  Price quote for a new water tower at the existing site would be $300k.
  • On our last sanitation survey, we were flagged for the vent and there was a small note on the hatches. The new package would meet the sanitation guidelines for the hatches.

CIP and Planning Committee (Darton)

  • We’re adding the silo to the CIP list

Old Business / Carryover Items

  • N/A.

New Business / Discussion Items

  • N/A

Other Business

  • N/A

What did we decide?

  • April: N/A
  • Clint: Will provide a microphone for Dave’s PC
  • Darton: Add silo to CIP list
  • Dave: N/A
  • Paul: N/A
  • Susan: N/A
  • Sam: New Pamphlet
  • Todd: Pre-construction loan and CWP (Consumer web portal)

Next Board meeting: Saturday, October 28, 2023 10:00 AM