Financial Summary – Q3 2023/2024

Financial Summary – Q3 2023/2024

Here’s a high-level summary of our financial position at end of Q3.

  •  on a straight-line budget a line item would be at 75%.
  •  Monthly Billings, at 83%, are ahead of budget as our Usage billings have risen after the lower billings in the fall.
  •  Bus Ops is high at 95%, but our biggest bills for the year are paid.  Will run over budget, at bit, by EOY.
  •  Projects are only at 27% as billings for PRV Engineering have slowly trickled in and work at Springs not started in earnest.
  •  We have total funds of $403k, more than expected for EOY.  Funds should continue to grow slightly through the Spring.

Click below for financial reports with greater account detail:

Leave a Reply

Your email address will not be published. Required fields are marked *